Skip to main content
Building Depot — Ontario's Authorized MegaDome Dealer for Engineered Fabric Buildings
Distribution & Warehousing Facility MegaDome fabric building in Vaughan, GTA
All case studiesCase Study · Commercial

Distribution & Warehousing Facility

Building Depot delivered a 120' × 300' × 26' MegaDome overflow warehouse adjacent to an existing third-party logistics distribution centre in Vaughan, adding 36,000 sq ft of clear-span storage on a 10-week schedule.

Vaughan, GTA 120' W × 300' L × 26' H· 10 weeks

The Customer

A GTA-based third-party logistics operator running a multi-client distribution centre off Highway 407. Inbound volume was outpacing the existing footprint and the operator was leasing offsite trailer parking to absorb the overflow — an expensive and inefficient stopgap.

The Challenge

The operator needed clear-span warehouse cover, fast, on a parcel adjacent to the existing DC. A conventional tilt-up build would have run 12–18 months. The roster of inbound customers couldn't wait. They needed a structure that the City of Vaughan and TRCA would permit quickly, with a roof tall enough for stacked pallet storage and an end-wall opening big enough for 53' trailers to back into.

The Solution

A 120' × 300' × 26' MegaDome on a concrete pier and thickened slab. Clear-span geometry meant no columns in the storage zone — pallet racking layouts were unconstrained. End wall included a 14' × 14' overhead door sized for full trailer access. Side walls included two personnel doors with vestibules. Stamped Ontario engineering and the Vaughan permit went in within three weeks of contract signing.

Why MegaDome Was Selected

MegaDome was selected because it gave the operator (a) a 10-week build window versus 12+ months for conventional tilt-up, (b) full clear-span at 120' width with no column interference for the racking grid, and (c) a capital cost roughly 30% lower than a comparable steel-and-cladding building at the same dimensions.

Construction Process

Construction ran 10 weeks. Site grading and underground services in week one, foundation pours weeks two through four, frame erection weeks five through seven, membrane and end walls weeks eight and nine, electrical and fire commissioning in week ten.

Foundation Construction

Drilled concrete piers around the perimeter carry the MegaDome arches, with a thickened slab in the racking zone designed for forklift wheel loads and standard pallet rack point loads. Anchor bolts were surveyed twice. The slab was poured in monolithic sections with engineered control joints and dust-rated finish.

Installation

MegaDome arches raised in three weeks. Membrane tensioned in the following week. End walls framed in light-gauge steel and clad, with the overhead door installed and commissioned by a specialist door contractor coordinated by Building Depot. Final electrical, lighting and fire detection commissioning by the operator's preferred trade partners on a Building Depot-coordinated schedule.

Building Specifications

Building dimensions120' W × 300' L × 26' H
Footprint36,000 sq ft, clear-span
FoundationDrilled concrete pier + thickened slab
End wall door14' × 14' overhead, full 53' trailer access
Side personnel doorsTwo, with vestibules
FrameHot-dip galvanized steel
MembranePVC, 25-year warranty

Project Results

  • 36,000 sq ft of clear-span overflow online in 10 weeks
  • Eliminated offsite trailer parking lease
  • Inbound dwell time reduced — trailers staged inside
  • Capital cost roughly 30% under conventional tilt-up
  • Permit issued in three weeks from contract signing

Customer Benefits

  • Capacity in weeks, not months
  • Clear-span layout means unconstrained rack design
  • Single turnkey contract through commissioning
  • Engineered for additional bays if volume grows
  • Lower per-square-foot capital cost than conventional steel

Project Gallery

Vaughan distribution warehouse during fabric installation

Need a building like this?

Building Depot is Ontario's Authorized MegaDome Dealer. Engineering, permits, foundation and turnkey installation — one accountable contract.

FREQUENTLY ASKED

Frequently Asked Questions

Related Solutions & Services

More Case Studies

READY TO BUILD?

Get a Building Depot Ontario quote in 24 hours.

Tell us your site, size and end use. Our Ontario engineering team will scope, price and schedule your fabric building.

Call Text Free Quote